Project experience / Distribution / Central Coast, BC

Nicknaqueet River

3.2 km · 34.5 kV distribution · 4.7 km fibre

The Nicknaqueet River connection brought power from a new hydroelectric powerhouse to Wuikinuxv Village, a remote First Nation community. R&R provided full EPC services for the 34.5 kV distribution line, including design, procurement, QA/QC, field installation, inspections, and construction and project management. The team completed the entire project while working within tight timelines and seasonal logistics constraints, coordinating the technical scope with the practical demands of delivering infrastructure to a remote community.

Scope and results

Project and challenge

Provide full design-build services for a 34.5 kV distribution-line connection from a new powerhouse under construction to Wuikinuxv Village, a remote First Nation community.

Role and execution

  • Line design and material procurement.
  • QA/QC, field installation and inspections.
  • Construction and project management.

Results

  • The entire project was completed within tight timelines while managing seasonal logistics challenges.