Back to experienceDiscuss a project

Team experience / Transmission / Southern BC

Interior to Lower Mainland

255 km · 500 kV

BC Hydro’s 255 km, 500 kV Interior to Lower Mainland line linked Nicola Substation near Merritt with Meridian Substation in Coquitlam, crossing rugged coastal mountains. Bill Robertson’s tower and line management through the Flatiron–Graham joint venture supported alignment, structure and foundation design, overseas procurement, permitting, forestry, survey and construction coordination. Constructability reviews enabled an early start; design reviews reduced the number of structures, and value engineering with BC Hydro achieved cost savings.

Scope and results

Project and challenge

The approximately half-billion-dollar design-build project expanded transfer capacity to the Lower Mainland for additional generation from Units 5 and 6 at Mica Generating Station. The 255 km line runs from Nicola Substation near Merritt to Meridian Substation in Coquitlam, across rugged coastal mountain terrain. Bill Robertson’s tower and line management was delivered through the Flatiron–Graham joint venture.

Role and execution

  • Route alignment and structure selection, design and field placement.
  • Foundation design and site constructability assessments.
  • Overseas tower-steel procurement; hardware design, procurement and delivery.
  • Conductor selection, procurement and installation.
  • Structure relocations to avoid avalanche hazards.
  • Forestry and occupant Licence to Cut permitting.
  • Field layout and route-alignment surveys.
  • Forestry cruising, waste and residue-clearing plans.
  • Stakeholder liaison.

Results

  • Practical constructability reviews enabled an early start to construction.
  • Ongoing QA/QC checks covered overseas material fabrication and field work.
  • Crew activities and equipment deployment were scheduled, with budgets prepared and monitored.
  • Clearing, logging and access-road development were coordinated through a unified approach.
  • Design reviews revised structure loadings and reduced the overall number of line structures.
  • Value engineering with BC Hydro achieved significant cost savings.