Project experience / Transmission / Vancouver Island, BC

Georgie Lake Transmission

40 km · 138 kV

R&R provided full EPC services to the AMEC–Black & McDonald joint venture for the 40 km, 138 kV Georgie Lake transmission line between Cape Scott Wind Farm and BC Hydro’s Port Hardy Substation. The team took on the assignment 13 months into a planned two-year program, managing permits, reconnaissance, access planning, surveys, procurement, pole installation, conductor stringing and commissioning. All work was completed in seven months, meeting a compressed delivery window.

Scope and results

Project and challenge

Provide full EPC services for the AMEC–Black & McDonald joint venture on a 40 km, 138 kV single-circuit line connecting Cape Scott Wind Farm with BC Hydro’s Port Hardy Substation. R&R took on the assignment 13 months into a planned two-year design-and-construction program and completed its work in seven months.

Role and execution

  • Occupant Licence to Cut permitting.
  • Navigable Waters Protection Act permitting for aerial crossings.
  • Centreline and right-of-way reconnaissance and access planning.
  • Pole and anchor layout and location surveys.
  • Procurement of all materials.
  • Complete line construction, including pole setting, conductor installation and commissioning.

Results

  • All work was completed in seven months after the team took on the assignment 13 months into the planned two-year program.